June 21st, 2004 – PAU established
June 9th, 2011 – PT Surya Esa Perkasa Tbk. (“SEP”) takes a 60% stake in PAU
March 13th, 2014 – Gas Sales Agreement (GSA) signed with JOB Pertamina, Medco and Tomori
Sept 5th, 2014 – Signed Loan Agreement with IFC (member of World Bank)
June 22nd, 2015 – EPC Agreement signed with PT Rekayasa Industri
August 2nd, 2015 – Groundbreaking, attended by President of Republic of Indonesia Mr. Joko Widodo
Dec 31th, 2015 – Progress overall project up to Dec 31, 2015 is 15.67 %
Dec 31, 2016 – Progress overall project up to Dec 31, 2016 is 76.81 %
Overall Progress Dec 31, 2017: 95.48%
Overall Progress Feb 28, 2018: 98%
April 28, 2018 – Mechanical Completion Date
Jul 7, 2018 – First Shipment
Sept 24, 2018 – First Commercial Shipment